The Story Behind
The Mezzanine floor Project
By CHRIS JOHNSON
So the first question you may have is how do you build a 2650sqm x 8.1m high mezzanine floor in just 8 weeks?
Well with a lot of material, team work, sweat, sandwiches, coffee & ice cream (yes ice cream on the hot days)
This projects was projects managed from site by RAXEL as Principle contractor compiling to all CDM 2015 & H&S regs. By Project Managing this project from site meant that the customer had a direct site contact for any questions or issues they had with the mezzanine floor.
By using a spider crane we were able to position all the steelworks with minimal effort, this also increased the amount of steelworks we were able to put up in a day.
This mezzanine floor has:
- 2 x 500kg capacity goods lifts
- 2x single pallet gates
- 2 x staircases
- enclosed with a mesh fencing with a logo printed certain fabric
- STOMMPY impact barriers to protect the main columns
- Partitioned walling for the landing area
- 32mm chipboard flooring